Professional Term Contract Fee Schedule

Approved Construction Budget Consultant Fee
<= $100,000 17.00% x Approved Construction Budget
$100,001 to $250,000 $17,000 + 16.0% of the amount over $100,000
$250,001 to $500,000 $41,000 + 13.0% of the amount over $250,000
$500,001 to $1,000,000 $73,500 + 10.5% of the amount over $500,000
$1,000,001 to $3,000,000 $126,000 + 8.1% of the amount over $1,000,000
$3,000,001 to $5,000,000 $288,000 + 7.0% of the amount over $3,000,000
$5,000,001 to $7,500,000 $428,000 + 6.0% of the amount over $5,000,000
$7,500,000 to $10,000,000 $578,000 + 5.0% of the amount over $7,500,000