Specialty Completion Date
2nd Year
Completion Date
3rd Year
Completion Date
4th Year
Notes:
Asbestos 7/1/2008 6/30/2009 6/30/2010 Pending Final Selection
Architectural 2/1/2008 1/31/2009 1/31/2010 In Contract Negotiations 
Balancing Services 2/28/2009 2/28/2010 2/28/2011  
Building Commissioning 3/14/2009 3/14/2010 3/14/2011  
Claim & Auditing Services 10/1/2007 9/30/2008 9/30/2009 In Contract Negotiations 
Construction Manager 11/30/2009 11/30/2010 11/30/2011  
Cost Estimating 3/31/2009 3/31/2010 3/31/2011  
Elevator Inspection Services 7/1/2010 7/1/2011 7/1/2012  
Energy 3/1/2010 3/1/2011 3/1/2012  
Energy Performance Program 8/1/2008 7/31/2009 7/31/2010 Pending Final Selection by Committee
Energy Performance Program 7/16/2010 7/16/2011 7/16/2012  
Engineering 12/31/2012 12/31/2013 12/31/2014  
Environmental 9/14/2010 9/14/2011 9/14/2012  
Environmental Management (SEQR) 10/1/2008 10/1/2009 10/1/2010 Proposals Under Review by Committee
Expediting       Pending Final Selection
Financial Advisory Services 11/13/2009 11/13/2010 7/13/2011  
Forensic Engineering Services 8/1/2009 8/1/2010 8/1/2011  
Geotechnical Engr & Soil Boring Srvcs. 3/22/2012 3/22/2013 3/22/2014  
Laboratory Planning and Design 9/30/2011 9/30/2012 9/30/2013  
Materials Testing 7/31/2009 7/31/2010 7/31/2011  
Printing 5/31/2009 5/31/2010 5/31/2011  
Printing of Official Statement 3/22/2010 3/22/2011 3/22/2012  
Relocation Management Services 4/1/2008 3/31/2009 3/31/2010 Notice to be placed in NYSCR 
Site Security 5/31/2009 5/31/2010 5/31/2011